|
Situation
"I have
a shift that works nights 16:00 to 00:30 with a half hour meal. They
work Mon, Tue, Wed, Thur, Sat, Off Fri and Sun."
"What
is the best way to set up their daily and weekly shifts in the
system?"
Payroll
Shift - An analysis
First let's look at some of the Payroll
Shift information that's immediately obvious from the above
information.
1) This is a basic 7 day night shift.
It's a 7 day Rolling Shift Cycle simply because that's the way
in which it is described. (If it had been described as "Two days on,
one day off" then it would be a 3 day cycle.)
Tip : Any shift that is described using
days of the week is normally a 7 day (or 14 day, 21 day etc) cycle.
2) It's a "night shift" - ie the
boundaries of the day are not at midnight (since they're still there
working at midnight.).
Arbitrarily pick a time when they're definitely not at work.
This is usually closer to the start time than the end time (since
people tend to work late rather than early). So I'll guess 12:00
midday is a good time for them. This is the Overlap Hours
setting - ie it's set to 12.
3) There are 2 possible options for an
employee during the week.
- come to work
- take the day off
Some sites may have more possibilities.
For example there might be a "short" day in the week - people often go
home earlier on Fridays and so on. But in this case there are 2
possible options for the day, so we need to make 2 Daily Shifts.
Daily Shift 1 - The Day Off
Let's do the simple shift first. Since
on the day off the employee isn't expected at work it's pretty easy to
create a simple empty day.
Now the biggest challenge here is
simply the lack of information. What's supposed to happen on a day off
if the employee does come to work? For the purposes of this
example I've simply made it up - you would obviously need to
substitute the details that occur at your site.

Not much exciting to see here - I've used OT 1.5 from 12:00 to 16:00
and then again from 30:00 (06:00) to 36:00 (12:00). In between I've
sandwiched some OT2.
Remember this is all here to cater for
the case where the employee does come to work, even though it's
his day off.
Tip : Notice that I've used the
12 hour offset we took note of in the previous section, and notice
also that my day is a nice regular 24 hours long. This isn't
necessarily required, but it makes things much neater.
The only other interesting part about
this day is that there is no schedule. ie He's not expected to work,
so the employee schedule is empty.
Daily Shift 1 - The Day Off
Again not too many details to go on, so
I'll make them up.

Pretty standard day. Again I've filled
in the slots from 12:00 to 36:00. On this day however, because
it is a working day, there is a schedule.

I've highlighted the 3 most interesting
things about this particular setup.
Firstly the schedule itself. Because it
goes over midnight the finish time is larger than 24:00. This simply
means that it goes into the following day.
The second key point is the Must be
Out By time. Notice the red line that marks where this is on the
time line.
Lastly always have a look at the blue
arrows below the time line. They show you at a glance if you've got
anything drastically out of order, or if you haven't used the right
times etc.
Payroll
Shift - Putting it all together
First add the shift.

Notice the Overlap Hours, and Rolling
Shift Cycle as we first spotted in the description. Notice also the
Auto-Process Time. Again it's set later than usual, as soon as I'm
confident that the whole shift must have clocked out.
The next bit again is a putting
together of what we already know;

First the days are nicely 24 hours
apart, notice all the starting times are offset by 12 hours from the
normal 7 day week.
Then on the Shift Details tab you can
populate each day with either the work day we created (the Non shift)
or the day off (the Noff shift).
Discussion
This would probably not be the end of
building this shift. There are lots more details that need to be
fleshed out. Balancing, Rounding, Holidays - all of these need to be
applied as necessary.
Nevertheless the above process forms
the building blocks for the shift, and gives you a skeleton on which
to hang all the details.
|